How much rent does Applied Digital’s new hyperscaler tenant pay?
About $2 million per megawatt a year, roughly 20% more than Applied Digital’s two earlier 300-megawatt leases
About $2.00 million per megawatt a year, by the method in Applied Digital’s own investor deck: the deck, filed with the SEC on Nov. 27, values the new 18-year, 150-megawatt lease at $5.40 billion and says rent “equals each lease’s base-term value divided by its term.” The same arithmetic on the deck’s table gives $1.67 million at Polaris Forge 3 and Delta Forge 1, $1.65 million at Delta Forge 2 and $1.79 million for CoreWeave’s 400 megawatts at Polaris Forge 1.
The company has not named the tenant; its Nov. 23 release called it a “tier-one investment-grade hyperscaler” and said only that the lease carried “higher pricing.” The deck says contracted capacity is subject to power supply agreement and regulatory approval conditions, lists a 100-megawatt Polaris Forge 2 expansion in Harwood, North Dakota, as “IN NEGOTIATION — NOT YET SIGNED,” and shows 275 megawatts online today. News Without Pictures first reported the per-megawatt comparison on Nov. 28.
- Applied Digital, Form 8-K Exhibit 99.1, investor presentation, November 2026 (filed Nov. 27, 2026): lease table p. 19, rent method p. 21
- Applied Digital, Nov. 23, 2026 release (Form 8-K Exhibit 99.1)
- News Without Pictures, Nov. 28: Applied Digital's unnamed tenant pays top rent per megawatt